Owner
Boulder Valley School District
Architect
klipp
Location
Boulder, CO
Project Size
32,098 sf
Delivery
CM/GC
Core Market

The Boulder High School project was a phased, partial gut and renovation of the 75-year-old main building. Major occupied facility issues included renovating a gymnasium under a tight, summer-only timetable to create a new weight room in time for football season. Scope included:

  • 22,300 sf gymnasium addition
  • Auxiliary gymnasium demolition
  • New 1,165 sf locker room building
  • New visitor’s entry
  • Bleacher renovation
  • 2,083 sf stagecraft and storage addition
  • New 2,550 sf administration addition
  • 4,000 sf administration area renovation
  • Food Laboratory gut and renovation
  • ADA upgrades
  • Reroute ceiling plumbing
  • Special Education area remodel
  • Replace electrical panels and fire alarms
  • Elevator addition
  • Master clock system replacement
Core Market